Accra-Tema Motorway reconstruction 48% complete – Construction consultant

Accra-Tema Motorway reconstruction 48% complete - Construction consultant
Facebook
Twitter
LinkedIn
WhatsApp
Pinterest
Facebook
Twitter
WhatsApp

By Amoako Kwame

The reconstruction of the Accra-Tema Motorway is 48% complete, with significant progress made on drainage infrastructure aimed at addressing persistent flooding along the corridor, according to the project’s construction consultant, Ing. Kwabena Bempong.

Speaking on Channel One TV’s The Point of View with Bernard Avle on Monday, July 13, Ing. Bempong said construction is currently focused on the urban highway, which will serve as a service road alongside the main motorway.

“We’re currently working on the urban highway, which is more like a service road. We’re currently at around 48%; we have not yet gone halfway through,” he said.

He explained that a significant portion of the work completed so far has involved the construction of drainage systems and interchanges designed to improve stormwater management and minimise flooding along the route.

According to him, managing traffic diversions around the interchanges and drainage structures has been one of the project’s biggest challenges.

“The challenges we have faced have mainly been the various diversions around the interchanges and the drainage structures,” he noted.

Ing. Bempong disclosed that the project includes the construction of about 20 culverts and three interchanges, with most of the major structures now nearing completion.

“We have about 20 culverts and three interchanges. We have constructed many of them, and the majority are almost complete. That has helped reduce flooding, and we did not experience the usual flooding,” he said.

He also assured motorists that contractors have taken steps to keep the motorway open to traffic throughout the construction period.

“We make sure the road remains passable throughout the construction period,” he stated.

His remarks come in the aftermath of the nationwide clean-up exercise initiated by President John Dramani Mahama following recent flooding that claimed lives, displaced residents and caused extensive damage to homes and infrastructure in several parts of the country.

The exercise, held on Friday, July 10, and Saturday, July 11, brought together the President, government officials, security agencies, local authorities and members of the public to desilt drains, clear choked gutters and remove refuse from flood-prone communities as part of efforts to reduce the impact of future flooding.

More Stories Here

Leave a Reply

Your email address will not be published. Required fields are marked *

Recent News

The Ghana Broadcasting Corporation is a giant electronic media (Radio and Television) organization tasked with a mission to lead the broadcasting industry through quality programming, which promotes the development and cultural aspirations of Ghana as well as undertaking viable commercial activities

Mission

To lead the broadcasting and communication industry through quality programming, which promotes the development and cultural aspirations of Ghana

Vision

To be the authentic and trusted voice of Ghana