Site icon GBC Ghana Online

BOST MD debunks claims of inflating cost of new office complex

bost

Story: Franklin ASARE-DONKOH

The Bulk Oil Storage and Transportation Company Limited (BOST), has denied allegations of inflating the cost of the construction of its single-unit tower.

Management of the company says claims that it padded the contract sum to $78 million are not only misinformed but also lack intellectual honesty.

The Minority in Parliament had hinted at a procurement scandal at BOST to the tune of $39 million.

According to the caucus, a contract sum for the construction of a single-unit tower estimated at $39 million was inflated and approved by the Public Procurement Authority (PPA) at $78 million, indicating a 100 percent inflated price.

Reacting to the allegation in an interview, the Managing Director of BOST, Mr. Edwin Alfred Provencal, claimed that the minority’s conclusion on the matter is based on a lot of misinformation and some intellectual dishonesty.

According to him, the contract was signed but, based on some circumstances, his predecessor thought that it should be looked into again.  “My philosophy on this matter is the fact that we do not have to mix politics and business,” he added.

The twin-office space was initially procured at $39 million under the previous administration but had to be halted in 2017 after allegations of inflated cost.

A value-for-money audit was subsequently carried out, resulting in a new value of $49.6 million for the office space.

However, BOST could not afford $49.6 million due to financial constraints and thus had to negotiate for a single block.

“Because we are not into the real estate business and we have liquidity challenges, we have decided that due to cash flow constraints, we cannot afford the two towers, so we opted for one, which the contractor agreed. We went to the PPA. They said there was a procurement irregularity that we needed to rectify before we go ahead to vary the contract to a single block.”

“It is that ratification request that we sent to PPA and the response that people saw and said we are buying a single block at $39 million.  But the final cost of the single building is $31 million and not $39 million or $78 million,” Mr. Provencal stated.

More stories here

Exit mobile version