By: Mabel Adorkor Annang
Prolonged blackouts that crippled local businesses and left thousands in darkness have come to an end following a major regulatory intervention. The Public Utilities Regulatory Commission (PURC), through its Central Regional Office, has facilitated the replacement of 10 damaged and overloaded transformers across several communities.
Carried out in collaboration with the Electricity Company of Ghana (ECG) at an estimated cost of GH¢550,000, the technical overhaul restores stable power to about 61,004 customers.

Prior to the intervention, affected communities endured severe service disruptions.
Gomoamaim was among the hardest hit, with roughly 4,000 customers experiencing power cuts lasting nearly two months.
In Saltpond Township, about 8,000 customers went without electricity for six weeks, while 7,500 customers in Anomabo suffered outages lasting up to a month.
Over 5,800 customers in Ajumako-Bisease faced a month-long outage, alongside similar disruptions in Katakyiase, Saltpond-Kurankyekrom, Cape Coast-Social Welfare, Nyankumasi Ahenkro, Agona, and Ekumfi Edukuma.
The widespread outages severely disrupted local commerce, particularly electricity-dependent enterprises such as cold stores, drinking spots, barbershops, salons, and provision shops.
Operators reported significant financial losses from wasted work hours, lost customers, increased operating costs, and spoiled perishable goods.
PURC prioritized the intervention with ECG after identifying the crisis through consumer complaints, field monitoring, and resident engagements. Urging the public to continue reporting service defects, the Commission emphasized that consumer feedback and regulatory oversight remain essential to identifying system failures and triggering swift corrective action.